• Was the screed for UFH? Is that length of time standard? Is the area totally off-limits when it is drying?

  • Rule of thumb for screed is that it cures at approx 1mm a day. I forget how long it is unusable for.

    Fast drying screed such as Ardex A38 is walkable from 3hours and ready for floor coverings from 4. Clearly more expensive than regular screed but a no brainer.

  • I think the 1mm a day only holds for relatively thin depths? if you have it deep to say bury UFH then it increases. Ours took months to go off enough to be able to lay LVT on.

    edit: 1mm a day for under 50mm, 0.5mm a day over 50mm is I think what we worked with.