Done by end of month hopefully.
This is the schedule I received from the builder however I'll say I'm sceptical of the handover date given potential COVID restrictions that may impact the schedule.4th Jan – 8th Jan
- Kitchen removal, remove tiles and clean sub floor.
- Install new boiler.
- First fix plumbing and electrics
11th – 15th Jan
- Plastering, floor preparation and floor tiling.
18th – 22nd Jan
- Install new skirting and paint room ready for kitchen install.
- Kitchen install (delivery 20/01)
25th Jan only
- Complete kitchen, 2 nd fix plumbing, electrics and fuse board change.
- (kitchen will be fully functional at this point apart from the kitchen tap.)
Once worktops have been fitted.
Install kitchen tap.
Complete hand over to customer. - Kitchen removal, remove tiles and clean sub floor.
Velocio
How long do you expect the work to take?