  • Done by end of month hopefully.
    This is the schedule I received from the builder however I'll say I'm sceptical of the handover date given potential COVID restrictions that may impact the schedule.

    4th Jan – 8th Jan

    • Kitchen removal, remove tiles and clean sub floor.
    • Install new boiler.
    • First fix plumbing and electrics

    11th – 15th Jan

    • Plastering, floor preparation and floor tiling.

    18th – 22nd Jan

    • Install new skirting and paint room ready for kitchen install.
    • Kitchen install (delivery 20/01)

    25th Jan only

    • Complete kitchen, 2 nd fix plumbing, electrics and fuse board change.
    • (kitchen will be fully functional at this point apart from the kitchen tap.)

    Once worktops have been fitted.
    Install kitchen tap.
    Complete hand over to customer.